PERI Weißenhorn
Production hall shell for Peri
We started stabilising the soil for this project on 4 August 2022 and celebrated the topping-out ceremony on 3 May 2023. Not only the short construction time is impressive, but also the quantity of material used:
- 3,200 m³ soil stabilisation
- 350 precast reinforced concrete parts
- 8,000 m² ground plate
- 5,000 m³ in-situ concrete
- 600 tons of reinforcing steel
- 1,000 m² brickwork
- 800 m² hollow walls
- 4,400 m² aerated concrete wall panels